Silvassa plant walkthrough
29 Jun, 11:20 · 14:32

Reviewed the tracker torque-tube line and galvanising bath. Agreed to add a second shift in August to cover the Khavda ramp.

Transcribed
Adani Green call notes
28 Jun, 16:05 · 22:10

Discussed the Khavda tracker dispatch timeline and pricing on the FY26 rate contract. Dispatch confirmed for 20 Jul.

Transcribed
Steel procurement review
27 Jun, 09:48 · 08:54

Flagged rising HR coil prices and low zinc stock. Lock forward cover before the next tracker run.

Transcribed
Production standup
26 Jun, 10:02 · 11:41

Backlog review. Transmission tower order at risk on schedule, follow up on plates. Tracker output strong.