Plyd

Silvassa plant walkthrough

29 Jun, 11:20 · 14:32Transcribed

Summary

Reviewed the tracker torque-tube line and galvanising bath. Agreed to add a second shift in August to cover the Khavda ramp.

Key points

  • Tracker line is at about 82% utilisation; roll-forming is the bottleneck.
  • Galvanising bath capacity is fine for the current mix.
  • A second shift was approved to cover the Adani Khavda dispatch.
  • Coating thickness is holding at the 85-micron spec.

Action items

  • Hire and onboard second-shift operators by 10 Aug.
  • Order additional HR steel coil for the tracker line.
  • Schedule a galvanising QA audit before the festive dispatch window.

Transcript

00:00
Rajiv

Let's start at roll-forming. Where are we on the tracker line?

01:12
Plant head

About 82% utilisation. Roll-forming backs us up, not galvanising.

03:40
Rajiv

For the Khavda ramp we'll need a second shift. Can we staff it?

04:05
Plant head

If we start hiring now, three weeks and we're covered.

08:50
Rajiv

And coating thickness?

09:30
Plant head

Holding at 85 microns, well within spec.