Plyd
Silvassa plant walkthrough
29 Jun, 11:20 · 14:32Transcribed
Summary
Reviewed the tracker torque-tube line and galvanising bath. Agreed to add a second shift in August to cover the Khavda ramp.
Key points
- Tracker line is at about 82% utilisation; roll-forming is the bottleneck.
- Galvanising bath capacity is fine for the current mix.
- A second shift was approved to cover the Adani Khavda dispatch.
- Coating thickness is holding at the 85-micron spec.
Action items
- Hire and onboard second-shift operators by 10 Aug.
- Order additional HR steel coil for the tracker line.
- Schedule a galvanising QA audit before the festive dispatch window.
Transcript
00:00
Rajiv
Let's start at roll-forming. Where are we on the tracker line?
01:12
Plant head
About 82% utilisation. Roll-forming backs us up, not galvanising.
03:40
Rajiv
For the Khavda ramp we'll need a second shift. Can we staff it?
04:05
Plant head
If we start hiring now, three weeks and we're covered.
08:50
Rajiv
And coating thickness?
09:30
Plant head
Holding at 85 microns, well within spec.